MT Group acting in joint venture with PPS Pipeline Systems has concluded the contract with Polish gas transmission system operator Gaz-System for construction of onshore gas pipeline for Baltic Pipe project in Poland.

Under this contract MT Group will be responsible for laying 41km of 1m diameter gas pipeline from Niechorze to Ploty in West Northern Poland. Contract also includes a construction of the Receiving Terminal in Konarzewo and the Gas Transmission Station in Ploty.

„We are proud to be a part of the project, which is significantly important not only for Poland, but also for the whole Europe. Preparation phase is over – now it is time for a complex and hard-working period. I am sure that our hands-on experience in the field of natural gas infrastructure and the team of professionals will ensure the best results and implementation on time,” says Simonas Kunickas, CEO of MT Group.

Almost 64 million Eur value contract was signed in November. The construction works have already been launched and expected to be completed by October 2022.

A strategic Baltic Pipe Project will enable gas flow from Norway to the Danish and Polish markets. The project is planned to be fully operational by 1st October 2022.