Hello from Finland! The works on site are in full swing! The target of this project is to construct a complex industrial structure of 400 m2 which will be located in a biofuel handling system within the territory of the power plant in Tampere, Finland. This industrial building will accommodate the large-scale equipment of biofuel handling system as well as complex electrical tools.

MT Group is handling the erection of steel structures, reinforced concrete slabs, sandwich walls and roofs. All the necessary steel structures are being manufactured by Nord Steel.

The structural frame of the building was mainly designed to comprise the steel frame in combination with the precast concrete elements. Preparation works were done precisely, so we are programmed for a successful performance.

The only thing that might surprise us on the way might be Finish winter weather conditions. But hey, Lithuania has chilly winters too!

The first stage is planned to be completed by the end of January 2022.